Mobile crane tandem offloading, hydraulic machine skates shifting, baseplate leveling, dial indicator shaft alignment, and pocket grouting.
Client / Sector
[Confidential Industrial Client in Pakistan]
Location (Pakistan)
Port Qasim Industrial Area, Karachi
Category & Scope
Mechanical Installation
Execution Status
Maintenance Retainer
1. Client Requirement & Operating Challenges
Imported multi-stage compressor and heavy slurry pump skids needed un-crating, indoor positioning, and precision alignment onto new concrete plinths.
2. Detailed Scope of Execution
Mobile crane tandem offloading, hydraulic machine skates shifting, baseplate leveling, dial indicator shaft alignment, and pocket grouting.
3. Engineering Solution & Methodology
Utilized precision optical leveling and dial indicators to align motor and compressor shafts to within 0.03mm tolerance.
4. Verified Result & Project Delivery
Successful uncoupled and coupled test run with zero vibration alarms.
Key Resources: Duration: 3 Weeks | Team: 8 Riggers & Millwrights | Materials: Non-Shrink Epoxy Grout, High-Tensile Anchor Fasteners, Stainless Steel Shims